Before the foundation walls go up, before the concrete is poured, before the framing starts, the ground has to come out. Excavation is the first physical step in building a new home in Vancouver, and what happens during those days sets the conditions for the whole project. This post explains what excavation involves on a typical Vancouver lot, how soil is handled and disposed of, what a geotechnical report is and when the City requires one, and what to plan for on sloped sites.
Every code reference below is from the BC Building Code 2024. City of Vancouver requirements come from the City's building permit process. Because vancouver.ca returns errors to automated requests, the notes below are based on the City's archived pages and common permit practice. Confirm current requirements with the City or your designer before submitting a permit application.
Excavation is the process of removing soil from the ground to create space for a foundation. On a typical Vancouver residential lot, the excavation contractor digs out the building footprint to the depth the structural drawings require.
For a full basement, that depth is usually enough to allow for the foundation slab, the structural walls, and usable headroom. The BC Building Code sets a minimum floor-to-ceiling height for a basement, and that height, plus the thickness of the slab and the floor assembly above, determines how deep the excavation must go.
For a crawl space, less depth is needed. The Code requires a minimum clearance between the ground and the underside of the floor joists, with enough room for access and for the mechanical services that run through the space.
The choice between a full basement and a crawl space affects the amount of excavation, the cost of the foundation work, and what can be done with the space below the main floor. That choice should be made with your designer before the permit drawings are prepared.
On a standard Vancouver lot, excavating for a full basement removes a large volume of material. The exact amount depends on the footprint of the building and the depth of the excavation. All of that material must leave the site, which requires trucks and coordination with the disposal destination.
The excavation contractor handles the removal, but the owner and the general contractor are responsible for confirming that the soil goes to a legally approved location.
Soil that is free of contamination can be accepted as fill at licensed fill sites, construction sites that need material, or at municipal facilities that accept clean fill. The contractor or hauler typically knows which sites in the Lower Mainland are accepting clean fill at a given time.
Before soil is accepted as clean fill at a regulated facility, the facility may ask for documentation confirming that the soil meets the standard for clean fill under BC's Contaminated Sites Regulation (the Regulation is BC Reg 375/96 under the Environmental Management Act). The contractor should obtain the necessary paperwork from the site before the trucks leave.
If the soil contains contaminants above the limits set in the Contaminated Sites Regulation, it cannot go to a clean fill site. It must go to a licensed soil treatment facility or a licensed hazardous waste disposal facility, depending on the type and level of contamination.
The Regulation applies when a property has a history of industrial or commercial use, when there is a known spill or release on the site, or when testing shows contaminant levels above the standards set in the Regulation. A Phase 1 Environmental Site Assessment reviews the site's history to identify whether further investigation is needed. A Phase 2 assessment involves soil and groundwater testing.
This work is done before or during the design phase. Finding contaminated soil after excavation has started, without a plan in place, creates delays and unexpected costs. If your lot has a history of commercial use or is in an area where contamination is common, budget for a Phase 1 assessment early.
A geotechnical report is a document prepared by a registered geotechnical engineer that describes the soil conditions on a site and gives recommendations for the foundation design.
The City of Vancouver requires a geotechnical report for many residential building permits, including:
- sites with slopes at or near the building footprint,
- sites near water, ravines or escarpments,
- sites where fill has been placed in the past,
- sites with a history of soft or unstable soil, and
- sites where excavation goes below the groundwater table.
The geotechnical engineer visits the site, drills test holes or uses other methods to sample the soil, and writes a report that the structural engineer uses to design the foundation. The City reviews the report as part of the building permit application.
Engaging a geotechnical engineer early in the design process is important. If the report finds soil conditions that require a more complex foundation, that changes the structural drawings, the excavation scope and the budget. Finding this out after the permit is submitted, or after excavation has started, is more expensive than finding it at the design stage.
Many Vancouver lots are sloped. Excavation on a sloped lot involves cutting into the uphill side and sometimes filling on the downhill side, depending on the design. The cut side of the excavation must be supported while the foundation is being built.
Temporary shoring, which is a system of walls and anchors that holds the soil back during construction, is often required. The design of the shoring is part of the geotechnical and structural engineer's work.
After the foundation is complete and backfilled, permanent retaining walls may be required to hold the grade around the building. In Vancouver, a retaining wall over 1.2 metres in height requires a building permit and must be designed by a licensed professional engineer. The retaining wall permit is often applied for at the same time as the building permit for the house.
The slope of the lot also affects drainage. The grading plan, which shows how water will drain away from the building, must be approved as part of the permit. Poor grading leads to water pooling against the foundation, which can cause problems over time.
A few things must happen before the excavation machine arrives on site.
Before any digging starts, the contractor calls BC One Call (a service that marks the location of buried utilities: gas, water, sewer, electrical, telecommunications). Digging through a live gas or electrical line is dangerous and illegal. The locate marks are painted on the ground or staked, and the excavation contractor works around them.
If there are trees on the lot or on neighbouring lots whose roots may be in the excavation zone, the City's tree bylaw and your permit conditions may require protection measures before excavation begins. Remove or protect trees according to the permit conditions, not according to what seems convenient on the day.
The City requires a construction fence around the site. This protects the public and contains materials on the lot. The fence must be in place before work starts.
After the soil is removed and the bottom of the excavation is at the right level, the foundation work begins. The excavation contractor grades and compacts the base. A drainage layer, typically granular fill, goes in before the concrete. The footings, foundation walls and slab follow in sequence.
This is the stage where any changes to the design cost the most to correct, because the foundation is permanent. If the geotechnical report recommended a specific slab thickness, compaction standard or drainage detail, those recommendations must be followed and confirmed by the inspector.
Excavation day is one of the most visible moments in a construction project. It is also one of the most consequential. We coordinate the soil haul, confirm the destination documentation, and have our supervisor on site when the machine is working near property lines, utilities or existing structures.
For sloped lots, we bring the geotechnical engineer to the site at the start of excavation to confirm that the soil conditions match the report, and again when the bottom of the excavation is reached, before the foundation contractor starts work.
When the foundation is complete and backfilled, the fill material placed around the foundation walls matters. The BC Building Code requires that fill be compacted in layers and that the material be appropriate for the purpose. Organic material (topsoil, peat, wood debris) is not acceptable as structural fill against a foundation, because it compresses over time and can allow the foundation to move.
On many Vancouver lots, the soil removed during excavation is not suitable for reuse as structural fill. It may contain organic material from the topsoil layer, or it may be too wet from Vancouver's rain to compact properly. The foundation contractor brings in granular fill (crushed stone or gravel) for the material placed directly against the foundation walls and under the floor slab.
This material cost is part of the foundation budget. It is worth asking your contractor what fill material they plan to use and why, before the work begins.
Before the first machine arrives on site, confirm the following with your general contractor:
- Has BC One Call been contacted and have all utilities been located and marked?
- Do you have the soil haul destination confirmed, including documentation for clean fill or a licensed facility for contaminated material?
- Has the geotechnical engineer reviewed the site and confirmed the excavation plan?
- What is the plan for temporary shoring if the excavation is adjacent to a property line or an existing structure?
- How is the site protected against rain? Does the schedule allow for the base of the excavation to be covered or protected before a prolonged rain?
A contractor who can answer these questions clearly before the work starts is a contractor who has planned the excavation properly.