Vancouver sits in one of the highest-risk seismic zones in Canada. Natural Resources Canada's seismic hazard maps place the city in a zone where the design ground motion is high enough that every new building has to be designed with lateral loads in mind. The BC Building Code applies this to houses the same way it applies to high-rises: every new home has a seismic design, and every framing inspection checks that the seismic design was built the way it was drawn.
This post explains what seismic design means for a new Vancouver house or multiplex, how the BC Building Code sets out the rules for small buildings, what the parts of a seismic system look like on the structural drawings, and what the City of Vancouver's framing inspector checks for on site.
Because vancouver.ca returns errors to automated requests, specific Vancouver By-law requirements below are based on the City's archived pages and common permit practice. Confirm current rules with the City of Vancouver or your designer before submitting a permit.
The BC Building Code uses the seismic hazard values from Natural Resources Canada. Vancouver's value is in the upper range for Canada. That value feeds into the design equations used to size the lateral system of every new building.
For a single detached house, a duplex or a small multiplex, the structure is usually designed under Part 9 of the BC Building Code, Housing and Small Buildings. Part 9 sets prescriptive rules for framing, connections and anchoring that produce a lateral system that meets the Code without a full engineering analysis.
For a larger or more complex building, including most multiplexes, a structural engineer designs the lateral system under Part 4, Structural Design. The engineer prepares the structural drawings, specifies the shear walls, hold-downs and connectors, and signs the Schedule B at the end of the project.
Vancouver's Building By-law requires a structural engineer on most new houses because of the local seismic hazard and the City's own requirements. Ask your designer whether your project is a Part 9 or a Part 4 design, because the paperwork and the on-site requirements differ.
A house has two kinds of load to carry. Gravity loads press down: the weight of the roof, the snow, the floors, the walls, and the people and furniture inside. Lateral loads push sideways: wind on the walls, and ground motion from an earthquake.
The lateral system is the set of parts that carries the sideways load from where it hits the building, down to the foundation. For a wood-framed house, the lateral system usually has three parts:
- The roof and floor diaphragms. These are the sheathed surfaces that transfer the load across the building to the walls below.
- The shear walls. These are specific walls built to resist the sideways load in the two main directions of the house.
- The connections. These are the hold-downs, straps, hangers and anchor bolts that tie everything together so the load can travel from the roof to the ground.
The structural drawings for the house show where each of these parts is, what it is made of, and what connections hold it in place. The framing crew builds it as shown. The inspector checks it before the walls are insulated and drywalled.
A shear wall is a wall built to resist a sideways load. In a wood-framed house, it is a stud wall sheathed on one or both sides with plywood or oriented strand board. The sheathing is nailed to the studs at a tighter spacing than a normal wall. The whole wall is anchored to the floor below with hold-downs at the ends, and to the floor above with sheathing that continues onto the floor above.
The structural drawings show which walls are shear walls. For each shear wall, the drawings specify:
- The sheathing type and thickness, for example 11 millimetre OSB or 12.5 millimetre plywood.
- The nail size, usually 2 1/2 inch common or ring-shank.
- The nail spacing at the edges of the sheathing and in the field.
- Whether the wall is sheathed on one side or on both sides.
- The hold-down model and location at each end of the wall.
A framer should treat the shear wall schedule on the drawings as a precise specification, not a guideline. A different nail size or a wider spacing produces a wall that does not meet the Code and will not pass inspection.
A hold-down is a steel bracket that ties a shear wall to the floor below. In a seismic event, the sideways load tries to overturn the shear wall. The ends of the wall want to lift up at one end and press down at the other. The hold-down resists the uplift and transfers it into the floor below, which transfers it into the foundation.
The structural drawings specify the hold-down model, the number and type of fasteners that go into the stud, and the anchor that ties the hold-down to the floor below or the foundation. For a wall on the main floor, the anchor is a bolt through the floor framing to a connector on the floor below. For a wall on the lowest floor, the anchor is a bolt into the concrete foundation.
A common framing deficiency is a hold-down that is installed with the wrong model, the wrong fasteners, or the wrong anchor. Another common deficiency is a hold-down that is installed correctly but with the stud drilled through by a plumber or electrician after the fact, which weakens the connection.
If a hold-down location conflicts with a plumbing or electrical line, the structural engineer needs to be consulted before the hole is drilled. There are often alternatives that preserve the connection.
A hold-down only works if the load can continue from the hold-down into the next part of the structure, and from there into the next, all the way to the foundation. This is called a continuous load path.
On a two-storey house, the load path goes from the roof framing, down through the second floor shear walls, into the second floor framing, down through the main floor shear walls, into the main floor framing, and finally into the foundation. At each connection, straps, hangers or bolts transfer the load.
The structural drawings show every connector on the load path. Common connectors include:
- Hurricane ties between the roof rafters and the top plate of the wall.
- Strap connectors between the top of one wall and the floor framing above.
- Strap or bolt connectors between the bottom of one wall and the floor framing below.
- Anchor bolts between the sill plate of the lowest wall and the concrete foundation.
A missing connector breaks the load path. In a seismic event, that is where the failure concentrates. The inspector checks every specified connector.
The lowest wood framing member in a wood-framed house is the sill plate. It sits directly on the concrete foundation. Anchor bolts tie the sill plate to the foundation.
The structural drawings specify the size and spacing of anchor bolts. Common requirements are 1/2 inch or 5/8 inch diameter bolts at a maximum spacing of 1.2 metres, with a bolt within 300 millimetres of each end of each piece of sill plate. The bolts are set in the concrete before it hardens, with the specified embedment depth.
A sill plate that is bolted at the wrong spacing, or with bolts that are too short, is a lateral-load failure point. The foundation contractor should set the bolts according to the drawings, not according to the foam board template that may come with the concrete forms.
The inspector checks anchor bolt size, spacing and embedment at the framing inspection, and compares them to the drawings.
Framing changes on site are a common cause of seismic design problems. A homeowner asks for a wider door opening in a wall that turns out to be a shear wall. A plumber needs to run a 4 inch stack through a stud that turns out to be at the corner of a shear wall. A framer decides to cut a pass-through between two rooms.
Any change to a shear wall, a hold-down location, or a stud that is part of the continuous load path has to go through the structural engineer. The engineer may approve the change as drawn, require a modification, or require a different approach. The engineer records the change in a site instruction or a revised drawing.
Doing this change without the engineer's involvement means the house is no longer built to the sealed drawings. This becomes a problem at the final inspection, when the structural engineer signs the Schedule C-B that certifies the structure was built to the design. The engineer cannot sign if the structure was changed in ways the engineer did not approve.
The City of Vancouver's framing inspector checks the seismic parts of the frame alongside everything else. The inspector looks at:
- Whether the shear walls are in the locations shown on the drawings.
- Whether the sheathing type, thickness, nail size and nail spacing match the drawings.
- Whether the hold-downs are the specified model, in the specified locations, with the specified fasteners into the stud.
- Whether the hold-down anchors are the specified size and are correctly embedded.
- Whether the specified connectors on the load path are installed, including hurricane ties, straps and hangers.
- Whether the anchor bolts between the sill plate and the foundation are the specified size and spacing.
- Whether any framing changes have been approved by the structural engineer.
A deficiency on any of these items is reported on the inspector's deficiency list. The framer corrects the deficiency, the inspector re-inspects, and the project continues after the re-inspection passes.
A multiplex has more mass than a single house, more walls, and a larger lateral load. A structural engineer designs the lateral system for every multiplex. The shear wall layout, the hold-downs and the connections are shown on the structural drawings.
In a multiplex, the shear walls often double as fire separations between units. The seismic design and the fire separation have to work together. The drawings show how the shear wall sheathing and the fire-rated gypsum board interact, and how penetrations through the wall are treated.
Sound separation between units is a third requirement that shares the same walls. The acoustic design, the fire design and the seismic design all affect the same walls, and the drawings have to resolve all three at once. A good structural engineer, a good designer and a good contractor coordinate these details before the framing begins.
We treat the structural drawings as a precise specification. Before the framing starts, we walk through the shear wall layout and the hold-down schedule with the framing crew so everyone understands what is required and where.
During framing, we check hold-down models and nailing patterns against the drawings before we close up any wall. We flag any site conflict between a shear wall and a plumbing or electrical line to the structural engineer before the work proceeds. We keep the engineer involved in any framing change that touches the lateral system.
At the framing inspection, we walk the site with the inspector. If a deficiency is found, we work out a correction with the structural engineer, implement it, and book the re-inspection.