A building permit gives you the right to build. It also gives the City of Vancouver the right to inspect the work at specific stages. Those inspections are mandatory, and each one is a hold point: the next stage of construction cannot proceed until the inspection at the current stage passes.
This post explains what the mandatory inspections are for a new home in Vancouver, what the inspector checks at each stage, what happens if you miss an inspection or fail one, and how the roles of the homeowner and the contractor relate to the inspection process.
Because vancouver.ca returns errors to automated requests, the notes below are based on the City's archived pages and common permit practice. Confirm current requirements with the City of Vancouver or your designer before beginning construction.
The BC Building Code and Vancouver's Building By-law set the minimum standards for how a building must be built. The permit drawings, which the City approved when it issued the permit, show how the specific building will meet those standards.
Inspections confirm that the work in progress matches the drawings and meets the Code. They happen at stages where the work is about to be covered up and would be difficult or impossible to inspect later. The foundation is inspected before concrete is poured. The framing is inspected before insulation and drywall. Rough-in plumbing and electrical are inspected before the walls are closed.
An inspector who finds work that does not comply issues a deficiency notice. The contractor corrects the deficiencies and calls for a re-inspection before the project can move forward.
The permit holder, usually the homeowner or the owner's representative, is responsible for requesting inspections. In practice, the general contractor typically manages the inspection schedule as part of their construction management work.
In Vancouver, inspections are booked through the City's online portal or by phone. The City may schedule the inspector for the same day or the next business day, depending on the queue and the inspection type. Book inspections in advance, with enough lead time to fit the inspector into the construction schedule.
The foundation inspection happens after the excavation is complete and the formwork or the structural elements are ready, but before the concrete is poured.
The inspector checks:
- The foundation layout matches the permit drawings, including the setbacks from property lines and the foundation dimensions.
- The depth of the footings matches the structural drawings and the geotechnical engineer's recommendations.
- The reinforcing steel is in place, correctly sized, and positioned with the right cover of concrete on all sides.
- The drainage layer and any under-slab requirements, such as a radon pipe and vapour barrier, are in place.
Concrete cannot be poured until the foundation inspection passes. This is the most time-critical inspection in the project, because the concrete crew is on site and the schedule depends on the inspection result.
The framing inspection happens after the structural framing is complete, the roof is sheathed, and the windows and exterior doors are installed, but before the insulation or drywall goes up.
The inspector checks:
- The framing matches the structural drawings, including the size and spacing of studs, joists and rafters.
- All required structural connections are made: hurricane ties, hold-downs at shear walls, post-to-beam connections.
- Openings for windows and doors are correctly sized and have proper headers.
- The roof structure is complete and correctly connected to the wall framing.
- Fire blocking and draft stopping are installed in the required locations.
- Stair framing and guardrail locations are ready for confirmation.
The plumbing rough-in inspection happens after the drain, waste and vent pipes are installed and the supply pipes are roughed in, but before the walls are insulated or drywalled.
The inspector checks:
- Drain, waste and vent pipes are the correct size, correctly sloped, and correctly connected.
- Cleanouts are accessible and in the required locations.
- Vent pipes are correctly connected and terminate above the roof at the required height.
- The water supply rough-in is in place with shut-off valves at each fixture location.
- Penetrations through fire separations are firestopped correctly.
Electrical rough-in inspection is conducted by Technical Safety BC, not by the City's building inspector. The electrical contractor books this inspection with Technical Safety BC. The building inspector may check that an electrical rough-in approval from Technical Safety BC is in place before allowing the insulation inspection to proceed.
This is an important point for scheduling. The electrical rough-in and the plumbing rough-in must both pass before the insulation inspection is requested.
The insulation inspection happens after the insulation is installed in the walls, floor and roof, but before the drywall goes up.
The inspector checks:
- The type and thickness of insulation matches what the energy advisor specified for the building's Energy Step Code target.
- Insulation is continuous with no gaps, and is correctly installed around penetrations and at the edges of the building.
- The vapour retarder (if required) is in place on the warm side of the insulation.
- Airtightness detailing at windows, penetrations and connections is complete.
If a blower door test is required for the project's Energy Step Code target, it typically happens at this stage, with a qualified energy advisor on site.
The final inspection is the last mandatory inspection before the City issues an occupancy permit. It happens when construction is complete and all previous deficiencies have been corrected.
The inspector checks:
- All work matches the permit drawings and all previous inspection deficiencies are cleared.
- Smoke alarms and carbon monoxide detectors are installed in all required locations and are operational.
- Guardrails and handrails are installed at the required heights and are structurally secure.
- Exterior finish is complete, including cladding, windows and doors, and site grading.
- Site grading directs water away from the building.
- The final plumbing and electrical connections are confirmed.
- The mechanical systems are operational.
The City will not issue an occupancy permit until the final inspection passes. No one may legally occupy the new home until the occupancy permit is issued.
If construction proceeds past a hold point without passing the required inspection, the inspector may require that work be opened up for inspection at the owner's cost. For example, if drywall is installed before the framing inspection passes, the inspector may require sections of drywall to be removed to confirm the framing behind it.
This is a situation that good scheduling and communication with the contractor prevents. Each hold point should be confirmed with the City before the next stage begins.
If an inspection fails, the inspector issues a written deficiency list. Work must not proceed past the failed stage. The contractor corrects each deficiency, then contacts the City to book a re-inspection. The City charges a re-inspection fee for each return visit.
After the re-inspection passes, work can proceed.
A common source of failed framing inspections is missing fire blocking. The installer may not have known exactly where the Code requires it, or a subcontractor installed a penetration after the fire blocking was done without reinstating it. Having the contractor and the supervisor walk through the fire blocking requirements before the inspection is booked reduces this risk.
The homeowner or the owner's authorised representative is the permit holder. This means the homeowner bears the legal responsibility for ensuring that inspections are requested and that the work complies with the permit. In practice, the general contractor manages the day-to-day scheduling of inspections on behalf of the owner.
The owner should know:
- Which inspections are required for their project.
- The expected timing for each inspection.
- That they should not occupy the home before the occupancy permit is issued.
- That they can request the inspection records from the City at any time.
For an owner managing construction without a general contractor, managing the inspection schedule is their direct responsibility.
We schedule inspections as part of our construction management process. For the foundation inspection, we confirm the booking with the City before the concrete crew is called in, so the inspection fits the pour schedule. For the framing inspection, we walk the site before booking to confirm that fire blocking, connections and rough-ins are all in place.
We give the homeowner a copy of each inspection record and flag any deficiencies and their resolution. The file of inspection records stays with the project documentation.